Logistics company, Bekasi · 2025
Distribution panel replacement over one weekend
Replacing a warehouse main panel with the shortest possible downtime.
What Made It Hard
The warehouse main panel was past its service life and no longer had circuit documentation. Replacing it meant cutting power to the whole warehouse, while operations ran six days a week on a tight dispatch schedule.
How We Handled It
The panel was assembled and fully tested at the workshop over the preceding four weeks, including labelling every circuit. That left three things to do on site: disconnect, install, and final testing. All of it was scheduled on a Sunday, the one day the warehouse does not operate.
What Was Delivered
- New main distribution panel, workshop tested
- Full circuit labelling and as-built drawings
- Recalculated breaker coordination
- Insulation and continuity test records
“Monday morning the warehouse ran as normal. Not one dispatch slot moved.”
Results
- 11
- Hours of downtime
- 1
- Weekend
- 0
- Working days affected
Let's Build Your Technology Roadmap, Together
From infrastructure and networking to security and communication systems, LTI has helped 540+ businesses across Indonesia run safer and more efficiently. Whatever stage you are at, whether planning a new system, upgrading legacy infrastructure, or looking for a long-term maintenance partner, our team is ready to map out a solution.